We have installed the pumps in the mechanical room, cored the holes from the roof to the mechanical room and started running the piping.

Project Manager: John Lyons

Preparations

Roof

START DATE COMPLETION DATE EVENT
7/6/2009 7/17/2009 core drilling
7/17/2009 7/24/2009 install riser piping
7/27/2009 Assemble steel tower stand at building
7/28/2009 Set up crane in front of building
Install cooling tower and stand
Crane piping and material to roof
7/29/2009 8/14/2009 install pipe stands
Install roof piping
install water make-up piping
install electrical
8/13/2009 Fill system with water and test cooling tower electrical
8/17/2009 8/21/2009 Building A/C will be shut down
8/17/2009 8/21/2009 Demo mech room
Install new heat exchanger
Install 2 new pumps building side
Pipe in equipment
8/21/2009 8/21/2009 Start up system
8/24/2009 Clean up and inspections