Atlantic Ocean Club

We have installed the pumps in the mechanical room, cored the holes from the roof to the mechanical room and started running the piping.
Project Manager: John Lyons
| START DATE |
COMPLETION DATE |
EVENT |
| 7/6/2009 |
7/17/2009 |
core drilling |
| 7/17/2009 |
7/24/2009 |
install riser piping |
| 7/27/2009 |
|
Assemble steel tower stand at building |
| 7/28/2009 |
|
Set up crane in front of building
Install cooling tower and stand
Crane piping and material to roof |
| 7/29/2009 |
8/14/2009 |
install pipe stands
Install roof piping
install water make-up piping
install electrical |
| 8/13/2009 |
|
Fill system with water and test cooling tower electrical |
| 8/17/2009 |
8/21/2009 |
Building A/C will be shut down |
| 8/17/2009 |
8/21/2009 |
Demo mech room
Install new heat exchanger
Install 2 new pumps building side
Pipe in equipment |
| 8/21/2009 |
8/21/2009 |
Start up system |
| 8/24/2009 |
|
Clean up and inspections |
Hyspy
Atlantic Ocean Club
We have installed the pumps in the mechanical room, cored the holes from the roof to the mechanical room and started running the piping.
Project Manager: John Lyons
Preparations
Roof
Install cooling tower and stand
Crane piping and material to roof
Install roof piping
install water make-up piping
install electrical
Install new heat exchanger
Install 2 new pumps building side
Pipe in equipment